Construction in the port of Granadilla, on the south side of the island of Santa Cruz de Tenerife (Canary Islands), of a 2,309 m long breakwater, consisting of the following elements:
- North breakwater, with a 596 m mound breakwater (topped with a shoulder at an elevation of +10.00)
- Vertical outer breakwater, with caissons 43.70 m long and a total of 1,713 m (the mooring depths of the caissons are between -16.00 and -24.00)
- A 135 m spur, will be constructed at the outer end of this breakwater,
In addition to these actions, other works were also carried out, such as the construction of 133 m of dock (Ribera dock), at -16.00 and with a ro-ro ramp. Also the perimeter enclosure parallel to the north breakwater 350 meters away from it, to create an esplanade at the back of the Ribera dock.